Project cargo shipping is not a bigger container move. The construction schedule sets the delivery order, and everything at the terminal has to bend to it. Here is how that work runs at Garden City Terminal and Ocean Terminal.

By Blake Handy, Project Cargo Specialist, Savannah Logistics Services  ·  20 minute read

Most calls I take about project cargo shipping through Savannah are not really about freight. Somebody has twenty seven units coming across three vessels, a millwright crew booked for week fourteen, and a cargo list they do not fully trust. They want to know whether all of that can be made to behave like one job.

It usually can. But it depends almost entirely on how early the conversation starts, and on whether the numbers on the cargo list match the equipment that actually got built. Everything else is execution.

Send your cargo list and we'll build a workable sequence, not a per-unit guess. Send Your Cargo List or call (912) 450-0202.

  • 25 years at the Port of Savannah
  • 80+ company-owned tractors
  • 300+ owned chassis
  • 15 miles from the SLS yard to the port gates
  • 2 hour quote response

What Project Cargo Is, and What It Is Not

Project cargo is freight that exists because a capital project exists. A plant, a substation, a mill, a process unit. It is usually several oversized or heavy units, sometimes across more than one vessel. What makes it project cargo is not the size of any one piece. It is that the units have to arrive in the order the construction crew can erect them, and that order is set by the job site, not by the ocean carrier.

Not the same as: Out of gauge describes one unit. Breakbulk describes how it is stowed. Project cargo describes why it is moving.

Project cargo shipping covers freight tied to a capital project. Industrial and energy projects do not run on freight invoices. They run on a construction critical path with a commercial operation date at the end of it. Every delivery date in the freight plan is worked backward from that date.

This is the part that gets missed in quoting. If a transformer is needed in week 39 and it lands in week 42, the construction program slips, commissioning slides, and the commercial operation date moves. The freight cost on that unit is almost never the largest number in that conversation.

Project cargo Georgia work has a local character. Manufacturing growth inland from the Georgia Ports Authority in automotive, battery, energy, and forest products means more multi unit programs arriving through Garden City Terminal, and, for breakbulk and roll on roll off shapes, through Ocean Terminal. Garden City is very fast at containers. It is not built to absorb project cargo handling that gets figured out on the day of discharge.

You are looking at project cargo when most of these are true

  • More than one unit, often across more than one vessel or bill of lading
  • Some units are out of gauge, breakbulk, or heavy enough to need engineered lifting
  • The erection sequence at the site drives the delivery order
  • One late unit idles a crew, a crane, or a plant startup
  • A forwarder, an ocean carrier, a terminal, and a local carrier all have to work from the same information

And the reverse. One flat rack going to one address is not a project. Treating it like one adds cost without adding control.

The Vocabulary That Actually Matters

Four words get used as if they mean the same thing, and each one costs money somewhere different. Getting them straight is the first practical step on any program.

Term What It Describes What It Means in Practice Where the Cost Sits
Project cargo (project cargo shipping, project cargo logistics) Why the freight is moving Multiple units tied to one capital project, delivered against an erection sequence Coordination, staging, and the cost of idle crews when a unit lands out of order
Out of gauge (out of gauge cargo, out of gauge container) The measurement of one unit The unit will not fit inside the envelope of a standard or high cube box Ocean freight and terminal surcharges. Over height, over width, and over length are priced separately
Breakbulk (breakbulk cargo shipping) How the unit is stowed The unit travels as itself and is lifted individually rather than inside a container Stevedoring, crane time, and engineered handling
Heavy lift (heavy and project cargo) What the lift requires The unit is heavy enough that vessel gear, shore cranes, and rigging have to be engineered around it Crane selection, method statement work, and specialized inland equipment

How Units Actually Travel

Four options cover most project cargo transport out of a container port like Savannah, and the choice is usually made at booking by somebody who will never see the unit.

Conveyance options

  • Flat rack. Flat rack shipping handles units that are over width or over height but still fit the terminal container system. Lashing design matters, and it has to account for how the unit will be lifted at discharge, not just at load.
  • Open top. Open top container shipping suits units that fit the box footprint but not the roof. A unit that fits is not automatically easy. If the lid, the lashing, or the lift arrangement is non standard, it still needs engineered handling.
  • Breakbulk on a multi purpose or heavy lift vessel. The unit travels as itself. Vessel choice includes whether the ship is geared, meaning it carries its own cranes, or whether the lift depends on shore cranes at both ends.
  • Roll on roll off. Wheeled and tracked equipment drives on and off rather than being lifted. Cheapest handling when the unit qualifies for it.

Sea fastening, dunnage, and lashing are the securing side of this, and they are governed by the load port and the vessel rather than by the receiving carrier. What matters on the discharge end is knowing what was done, because how a unit was secured determines how long it takes to release it and what condition it arrives in. For the full ocean side treatment, see our companion piece on out of gauge freight excellence at the Port of Savannah.

What It Takes to Move Project Cargo Successfully

Ask people who have run these programs for twenty years what separates the ones that work from the ones that go sideways, and the answers are consistent. Almost none of them are about trucks.

Seven things that decide the outcome

  • Start while the equipment is still being fabricated. Engineering, crane reservations, specialized trailers, and permits are cheap to arrange months out and impossible to compress later. The single most common cause of a blown schedule is a first conversation that happened after the booking was confirmed.
  • Verify the cargo list against what was actually built. Dimensions and weights on a supplier cargo list are often carried forward from a design revision. Check twice, once from drawings and once physically.
  • Get the engineering done in advance. Lift plans, method statements, route surveys, and utility checks along the inland route. All of it has a lead time and none of it can be produced on the day the vessel berths.
  • Keep one party accountable. Ocean, terminal, inland, and placement inside one accountable scope beats four vendors with four contracts. Not because vendors are careless, but because the gaps between contracts have no owner.
  • Put real contingency in the schedule. Vessels arrive late. Sites are not ready. Weather closes a route. Contingency belongs in the plan, not in the explanation afterward.
  • Use people who know the specific port and corridor. Generic competence does not transfer. Somebody who has run wide units through these gates knows things about Garden City and Ocean Terminal that are not written down anywhere.
  • Own the terminal clock. Free time on out of gauge units is short. Somebody has to be watching it by name, with authority to move equipment.

Every one of those is a planning discipline rather than a capability. That is the honest answer about project cargo solutions. The equipment side is largely a solved problem. Any competent operator can find a lowboy. What separates providers is whether the work in front of the equipment got done.

Send the Cargo List While the Units Are Still Being Built

We work the terminal assignment, staging, delivery sequence, and inland plan against your erection dates. Early costs nothing. Late costs the schedule.

Talk to a Project Cargo Specialist. Quote response within two hours during business hours, live answer around the clock. Talk to a Project Cargo Specialist or call (912) 450-0202.

The Freight Schedule Comes From the Construction Schedule

This is the idea that makes everything else make sense. Units arrive in the order the ocean carrier and the booking put them on ships. They have to be installed in the order the construction contractor can erect them. Those two orders almost never match.

A base skid gets fabricated early and ships early, or it gets fabricated late and ships last. The enclosure it sits inside might sail first. On the site, the base has to be set before the drive unit, and the drive unit before the enclosure. Deliver in arrival order and you put a roof on the pad before the foundation exists.

Reconciling those two orders is the whole job. It is done in one place, which is a yard near the port where units can wait cheaply until the site can take them.

Arrival Order (set by vessel schedule) Erection Sequence (set by the site)
Vessel 1 — Enclosure, controls First — Base skid
Vessel 2 — Base skid Second — Drive unit, OOG
Vessel 2 — Drive unit, OOG Third — Piping, breakbulk
Vessel 3 — Piping, breakbulk Fourth — Enclosure, controls
Vessel 3 — Containers Last — Containers

Figure 1. A staging yard roughly 15 miles from the port gates reconciles the two orders, holding units until the site can receive them without accruing terminal storage. The enclosure lands first and installs fourth — delivering in arrival order would put a roof on the pad before the base exists. Illustrative; the real sequence comes from the customer cargo list and the erection contractor.

The Cargo List Is the Document Everything Depends On

The cargo list carries dimensions, weight, lift points, center of gravity, and marking for every unit. Vessel selection, terminal assignment, crane sizing, trailer selection, and permit classification are all derived from it. Nothing downstream can be more accurate than that document.

It is also, routinely, wrong. Not through negligence. A supplier issues a cargo list off a design revision, the unit gets built slightly differently, and nobody circles back. By the time a crane operator finds out, the vessel is on the berth and eighty tons is in the air.

Cargo List Field What It Determines What Happens When It Is Wrong
Dimensions Conveyance, terminal assignment, receiving equipment The wrong trailer shows up and the unit cannot be gated
Weight Crane sizing, lift plan, and whether the inland move is legal or permitted The crane is undersized and the lift is refused at the berth
Lift points and center of gravity Rigging arrangement and the method statement where cranes are involved The hook waits while somebody works out how to pick it safely
How the unit is stowed Flat rack, open top, breakbulk, roll on roll off, or standard container The program is quoted against the wrong terminal and the wrong tariff
Erection sequence Which units are on the critical path and which can wait in a yard Units deliver in booking order and the site cannot use them
Site ready date per unit How long staging is needed and where cargo waits A unit delivers into a site that is not ready and gets turned away at the gate
Marking Identifying the right unit among forty similar crates Time lost at the yard finding what shipped, and the wrong crate delivered

Two habits follow. Verify dimensions twice, once from drawings and once physically. And put one named person in charge of the current version, with a phone that gets answered. Not a shared folder and not a distribution list.

Handling at Garden City Terminal and Ocean Terminal

Savannah runs two facilities that matter to project cargo, and they behave differently. Getting the terminal assignment right at booking is worth more than any negotiation that happens afterward.

Facility What It Handles What to Plan For
Garden City Terminal Containerized project cargo including flat racks, open tops, and the containers moving with the project Container velocity is high and free time on out of gauge units is short. Gate out gets planned, not reacted to
Ocean Terminal The Georgia Ports Authority breakbulk facility. Breakbulk, roll on roll off, heavy lift, steel, and forest products, with covered and open storage Method statements, crane coordination, and stevedore scheduling drive the timeline more than gate hours do

The Authority's preference on many out of gauge and non containerized moves is shipside or direct transfer, meaning vessel hook straight to the receiving truck, or the reverse on export. When that cannot happen, cargo goes to first point of rest and the storage clock starts. A program that discharges eight out of gauge units and arranges equipment afterward will be paying storage before the second unit is gated.

Where an ocean configuration will not travel legally on the highway, transloading services in Savannah convert the load into a movable shape before the first mile. That decision belongs in the original plan. Discovering it at the yard gate costs a day and a crane.

Get the Gate Out Plan Built Before Discharge

TWIC cleared drivers, owned equipment staged locally, and a named point of contact watching free time on every unit. 25 years working project cargo at Garden City Terminal and Ocean Terminal.

Request a Handling Plan. Request a Handling Plan or call (912) 450-0202.

The Documents That Stop a Hook

Project cargo transportation fails on paperwork far more often than it fails on equipment. Nothing breaks. A document simply has no owner, and eighty tons sits under a crane while people look for it.

Five documents worth assigning by name

  • The cargo list. Dimensions, weight, lift points, center of gravity, marking. Every other decision comes off this. Assign one owner for the current version.
  • The method statement. The written plan for how a non standard unit gets lifted, handled, stowed, and secured, including a risk assessment. The Georgia Ports Authority charges for this work when Authority or leased cranes are in the lift. If nobody was assigned to prepare it before the vessel is on the berth, the hook waits.
  • The delivery order and gate release. Terminal authorization to release a specific unit to a specific carrier. Written against the wrong equipment type and the unit stays where it is.
  • The declared weight. A stevedore who was given an optimistic number will refuse the lift, and should. Declared weight has to match the unit, not the purchase order.
  • The dock receipt, on export. Non containerized export cargo arriving by truck is preferred as shipside delivery. If the vessel window slips, somebody needs to have already agreed to own the extra terminal charges.

One more worth knowing about. On heavy lift programs the cargo underwriters sometimes appoint a marine warranty surveyor, whose approval of the lift and securing arrangements is a condition of cover. That is a load port and voyage role rather than a discharge role, but the approved method statement and its conditions can carry through to discharge. Worth asking early whether one is appointed on your program, because it changes who has to sign off on a change.

The Inland Leg and Where It Hands Off

Once a unit clears the gate it enters a different rulebook. The ocean side runs on tariffs and terminal procedure. The highway runs on state permits. Georgia legal limits are 8 feet 6 inches wide, 13 feet 6 inches high, and 80,000 pounds gross on five axles. Above any of those, the unit needs a permit before it moves.

For planning purposes the thresholds matter less than the lead time. Ocean transit is measured in weeks and carries slack. Permit approval on the biggest units is measured in weeks too, and carries none. A permit needing bridge and structural review will not compress because a vessel arrived early. That is why the inland leg gets designed at booking rather than at discharge.

Trailer selection, permit tiers, escorts, route surveys, and multi state routing are covered in full on our heavy haul trucking at the Port of Savannah resource. What a project cargo plan needs from the inland leg is narrower and it comes down to three fields per unit.

Three fields, added to the cargo list, per unit

  • Classification. Legal, permitted, or superload. Derived from the dimensions and weight already on the list.
  • Lead time. Routine permits are quick. Anything requiring structural review is not.
  • Route constraints. Posted bridges, overhead lines, turning radius at the plant gate. The last mile stops more units than the interstate does.

Three columns on a spreadsheet. They are the difference between a program with a schedule and a program with a hope.

Heavy and project cargo programs are where these two rulebooks meet on one shipment. A single program can include ordinary containers pulled routinely by drayage companies in Savannah GA alongside one unit that needs an engineered route survey. Both belong on one plan and one radio net.

Project Cargo by Sector in Georgia

Project cargo Georgia work clusters around the industries that have been building inland from the port. Each sector brings a different constraint, and the constraint predicts difficulty better than the dimensions do.

Sector Typical Units The Real Constraint What It Means for the Plan
Energy and utility Transformers, generators, turbines, switchgear, substation modules Outage windows. The receiving window can be a single weekend No schedule tolerance. Staging is mandatory, not optional
Battery and EV manufacturing Coating lines, formation equipment, dry room modules, press frames Fixed erection sequence and clean handling requirements Arrival order rarely matches erection order. Yard staging carries the program
Forest products and paper Machine sections, dryer cans, rolls, structural steel Weight concentration and mill site access Ocean Terminal handling plus a tight last mile into established mill sites
Automotive and manufacturing Presses, robots, conveyor sections, machine tools Millwright and commissioning crews contracted for fixed dates The crew calendar drives delivery. Freight bends to it
Construction and infrastructure Girders, precast elements, plant equipment, cranes Site readiness, which moves constantly Dates get revised repeatedly. Flexible staging is the whole value
Chemical and process Reactors, columns, vessels, skid mounted process units Lift engineering and foundation tolerance Method statements and rigging plans dominate the timeline

The common thread is that in every sector the binding constraint sits downstream of the freight. Nobody builds a project schedule around when a vessel can berth. They build it around when a crew is on site. Project cargo companies that start at the vessel and work forward will always be arguing with the customer's actual schedule.

Forwarders, Carriers, and the Gap Between Them

Project cargo freight forwarders earn their fee on ocean allocation and chartering, origin control, insurance, and customs across multiple countries. That work is real and specialized. It does not replace somebody who can put equipment under the hook in Pooler on a Tuesday.

The handoff is where time leaks. A forwarder books the slot. The carrier files the out of gauge declaration. The terminal needs a method statement. A trucker finds out the unit will not travel in the configuration it arrived in. Every party did their job correctly and the program still missed the date, because five specific things sat between the contracts with no owner.

Forwarder Owns The Gap — Usually Nobody Local Carrier Owns
Ocean allocation and chartering The current version of the cargo list Terminal execution and gate out
Origin consolidation Who watches terminal free time Staging near the port
Cargo insurance Who prepares the method statement Inland delivery
Customs documentation Who sets the delivery order against the erection sequence Rigging and lift
Multi country coordination Who pays when the site slips Final placement

Figure 2. Neither scope is deficient. The five items in the middle column have no default owner, which is exactly why they need to be assigned in writing before booking. Most program failures happen in that unassigned middle rather than inside either party's scope.

When SLS is brought in on the port and inland side, we ask for the whole cargo list rather than the three problem units. The containers moving with the project still have to be pulled, and they have to be pulled by somebody on the same thread as the crew handling the oversized pieces. Split vendors with nobody owning sequence is exactly how a crate arrives three days before the skid it bolts to.

Staging, Rigging, and Final Placement

Units do not all leave the terminal on the same day, and sites are rarely ready to take everything at once. Staging near the port is part of the plan, not an add on. A secure yard roughly 15 miles from the gates lets a unit wait until the one before it is set, without burning terminal free time and without delivering into a site that cannot receive it.

Final placement is the part most freight quotes leave out. The job is not done when the trailer reaches the plant. The unit still has to come off the deck, travel the last few hundred feet, and land on a foundation to tolerance. That needs rigging: slings, spreader bars, jacking and skating gear, and a lift plan built against a verified weight and center of gravity. Shippers searching for rigging companies in Savannah GA, machinery transport, or heavy lift crane support are describing pieces of this same scope.

A millwright installs, aligns, maintains, and dismantles industrial machinery. Millwright work starts where the freight scope traditionally stops. Holding both under one contract removes the most common reason a delivery stalls, which is a unit sitting on a trailer in a plant yard while two contractors argue about whose lift it is.

“Execute and good things will happen.”
— Blake Handy, Project Cargo Specialist, Savannah Logistics Services

For the full vessel to foundation walkthrough, see our piece on project cargo at the Port of Savannah from vessel to final placement.

How Project Cargo Is Priced

By program, not by unit. A per unit rate quoted without a cargo list is an estimate and it will be revised. Knowing the components makes it possible to compare two proposals that look nothing alike on the surface.

Component What Drives It How to Control It
Ocean freight and out of gauge surcharges Dimensions per unit. Over height, over width, and over length price separately Verify dimensions before booking. Small reductions can drop a unit into a cheaper band
Terminal handling and stevedoring How the unit is stowed and whether the lift is standard or engineered Fix the terminal assignment at booking rather than on arrival
Method statement and engineering Non standard lifts, particularly where Authority or leased cranes are involved Assign an owner early. Chargeable work with a real lead time
Terminal storage Time beyond free time, which is short on out of gauge units The most avoidable cost in project cargo. Plan gate out before discharge
Staging How long units wait between gate out and site readiness Far cheaper than terminal storage. Budget for it deliberately
Inland delivery Classification per unit, plus permits and escorts where required Classify every unit while planning, not at dispatch
Rigging and final placement Lift complexity, crane sizing, site access, foundation tolerance Put it in scope from the start. Bolting it on later costs more
Coordination Unit count, number of parties, and how often dates move Real cost, and the cheapest line on the invoice relative to what it prevents

The cost nobody quotes

Idle time at the site. A commissioning crew standing down for three days because a unit landed out of sequence usually costs more than the entire inland bill for that unit. When you are comparing project cargo proposals, the useful question is not which quote is lower. It is which provider is more likely to protect the date.

Get a Program Price, Not a Per Unit Guess

Send the cargo list and the erection dates. We come back with a sequence and costs attached to each stage, so you can see where the money and the risk actually sit. Two hour quote response during business hours.

Request Program Pricing. Request Program Pricing or call (912) 450-0202.

How to Evaluate a Project Cargo Partner

Seven questions separate operators who can run a program from operators who can quote one.

Ask these before you award the work

  • Who owns the current version of the cargo list? Name the person, not the department.
  • Is the equipment owned or sourced? Owned equipment can be reassigned. Sourced equipment can be unavailable.
  • Who watches terminal free time, and who pays if it runs out? If nobody answers, the answer is you.
  • Where does cargo wait if the vessel or the site slips? If the answer is the terminal, the answer is a storage invoice.
  • Can the same desk pull the containers moving with the project? If not, expect sequence problems.
  • What happens when the cargo list turns out to be wrong? It will be, at least once. The answer tells you whether there is a process or a hope.
  • Who sets the unit on the foundation? If nobody in the quote does, the quote is incomplete.

Trucking companies in Savannah GA that live on stacked boxes are essential to this port and good at what they do. That does not make them project cargo handling services. The practical test is whether one desk can talk about method statements, terminal gate procedure, staging economics, and a turning radius at a plant gate in a single conversation without transferring the call.

Frequently Asked Questions

What is project cargo?

Project cargo is freight that exists because a capital project exists. It is usually multiple oversized, overweight, or high value units belonging to one plant, substation, mill, or facility. What makes it project cargo is not the size of any single unit but the fact that the units have to arrive in the order the construction crew can install them. The construction schedule drives the freight schedule, not the other way around.

What is project cargo shipping?

Project cargo shipping is the work of getting a multi unit industrial shipment delivered in the order the receiving site can erect it. It covers vessel selection and stowage, terminal handling, documentation, gate out, staging, inland delivery, and setting the unit on its foundation. The freight is usually straightforward. Keeping the sequence intact while dates move is the hard part.

What does it take to move project cargo successfully?

Seven things. Start planning while the equipment is still being fabricated. Verify the cargo list against the units that were actually built. Get the engineering done in advance, including lift plans, method statements, and route surveys. Keep one party accountable rather than a chain of vendors. Build real contingency into the schedule. Use people who know the specific port and corridor. Own the terminal clock so free time does not expire while equipment is being arranged.

What is a cargo list in project cargo?

The cargo list is the working document that carries dimensions, weight, lift points, center of gravity, and marking for every unit in the shipment. Vessel selection, terminal assignment, crane sizing, trailer selection, and permit classification are all derived from it. Cargo lists are frequently built from a design revision rather than the unit that was fabricated, which is why dimensions get verified twice, once from drawings and once from a physical check.

What is the difference between project cargo and breakbulk?

Breakbulk is how cargo is stowed. The unit travels as itself and is lifted individually rather than inside a container. Project cargo describes why the freight is moving, which is a capital project. One project shipment can contain breakbulk units, flat racks, open tops, roll on roll off units, and ordinary containers at the same time.

What is the difference between project cargo and out of gauge cargo?

Out of gauge describes one unit that will not fit the envelope of a standard container. Project cargo describes a shipment tied to a construction program. A project can be made entirely of units that fit standard containers, and a single out of gauge container may have nothing to do with a project. The terms are not interchangeable.

What information is needed to quote project cargo at the Port of Savannah?

A complete cargo list with dimensions and weight for every unit, lift points and center of gravity, how each unit is stowed, origin and destination, the vessel window if it is known, and the date the site can receive each unit. Without the erection sequence a quote can price the freight but cannot protect the schedule.

Which Savannah terminal handles project cargo?

Garden City Terminal handles containerized project cargo including flat racks and open tops. Ocean Terminal is the Georgia Ports Authority breakbulk facility and handles breakbulk, roll on roll off, heavy lift, steel, and forest products. Many project shipments touch both, which is why terminal assignment belongs in the plan before the vessel sails.

What is a method statement?

A method statement is the written plan for how a non standard unit will be lifted, handled, stowed, and secured, including a risk assessment. On heavy lift work it is reviewed for adequacy before the operation. The Georgia Ports Authority charges for method statement work when Authority or leased cranes are involved in the lift. If nobody has been assigned to prepare it before the vessel is on the berth, the hook waits.

How is project cargo priced?

By program rather than by unit. The components are ocean freight and out of gauge surcharges, terminal handling and stevedoring, method statement and engineering work, terminal storage beyond free time, staging, inland delivery including permits and escorts where needed, rigging and final placement, and coordination time. A per unit rate quoted without a cargo list is an estimate and it will be revised.

Do project cargo freight forwarders replace a local carrier?

No. Forwarders handle ocean allocation and chartering, origin consolidation, insurance, and customs. A local asset based carrier handles terminal execution, gate out, staging, inland delivery, and final placement. The two roles are complementary, and most schedule failures happen in the handoff between them rather than inside either scope.

What is a millwright and why does project cargo need one?

A millwright installs, aligns, maintains, and dismantles industrial machinery. Project cargo needs millwright capability because the job is not finished when the trailer reaches the site. The unit still has to come off the deck, move the last few hundred feet, land on its foundation, and be aligned to tolerance before the plant can commission it.

How SLS Runs Project Cargo

Savannah Logistics Services has moved project cargo, out of gauge, and breakbulk freight around the Georgia Ports Authority for 25 years. The fleet is asset based: roughly 80 company tractors, more than 300 owned chassis, and the specialized equipment project cargo transport requires. Rigging and millwright capability are in house, which means the scope runs from vessel discharge through final placement rather than stopping at a plant gate.

The yard on Morgan Lakes Industrial Boulevard in Pooler sits roughly 15 miles from the port gates. That proximity is not marketing. It is what makes it possible to hold unit B until unit A is set without paying terminal storage, and to work against a live vessel schedule instead of a broker's availability.

None of this is complicated. It is just work that has to be done before the vessel arrives rather than after. Plans are inexpensive. A unit on the pad, on the date the crew can use it, is the only measure that counts.

About the Author

Blake Handy is a Project Cargo Specialist at Savannah Logistics Services, working out of the company's Pooler, Georgia facility near the Port of Savannah. He coordinates multi unit project shipments across ocean, terminal, inland, and final placement scopes for industrial, energy, and manufacturing customers moving freight through Garden City Terminal and Ocean Terminal.

Continue Reading on Specialized Freight at the Port of Savannah

The resources below go deeper on the ocean side, the inland side, and the capabilities referenced throughout this article.

Send the Cargo List

Dimensions, weights, lift points, the vessel window, and the date the site can receive each unit. The SLS project cargo desk responds within two hours during business hours with a workable sequence rather than a generic per unit rate.

Request a Quote  |  Call (912) 450-0202

Savannah Logistics Services · Morgan Lakes Industrial Boulevard, Pooler, Georgia · Serving the Port of Savannah and the Port of Charleston

Editorial note. Georgia Ports Authority tariffs, terminal free time, and state permit thresholds are revised periodically. Figures here are for planning reference as of August 2026. Confirm current requirements with the issuing agencies and with your carrier before every move.